2016-17 Construction Projects 

Projects below are scheduled for the 2016-2017 season here in Auburn.   For more details, be sure to check out the Public Services/Engineering Weekly Reports that can be found in the menu to the left.   For additional questions or concerns, feel free to send us a message via Contact Us. 

  Updated 5/18/2017


  • 2017 Reclamation Project – Crews have started loam, seed and mulching. Prepping for surface pavement the next two weeks. Surface pavement

  • 2017 MPI Project – Hampshire St- drainage is currently being installed

  • Ash Landfill forced sewer main – project to be advertised for bid May

  • Park Ave Reconstruction – project has resumed

  • Turner Street sidewalks – project has resumed

  • 2017 Reconstruction Project – Lake St- final plans are being prepared

  • 2016 Reclamation Project – Pownal Rd from Trapp Rd to Jordan School Rd– project to start mid May

  • Sopers Mill Bridge Rehab – Project to bid May

  • Pettingill Pond Dredging – permitting- NRPA permit received

  • Cook Street Reconstruction – Bids have been opened. Project to start June 1

  • 2017 Culvert grant application – The City has been awarded a $95,000 grant for the project

  • 2017 Tree Inventory Grant – The City has been awarded a $9,000 grant for this project

  • 2016 MPI South Main St – in construction- surface pavement scheduled first week of June

  • Hampshire Street – Project has started with pipe cleaning

  • General Consulting Services – Woodard & Curran has been selected