2016-17 Construction Projects 

Projects below are scheduled for the 2016-2017 season here in Auburn.   For more details, be sure to check out the Public Services/Engineering Weekly Reports that can be found in the menu to the left.   For additional questions or concerns, feel free to send us a message via Contact Us. 

  Updated 8/11/2017

 

  • 2017 Reclamation Project – Perkins Ridge Road has been completed.  Pownal Road drainage work is complete. Re-claimed Trapp Road to Jordan School Road.  Base paving section from Trapp Road to Partridge Lane completed.  Gravel is being added to section from Partridge Lane to Jordan School Road.

  • 2017 MPI Project – Hampshire St- Base paving between Union Street and Gamage Avenue completed. Curb and utility work continues in the paved section. The storm drain line pipe lining is complete

  • Ash Landfill forced sewer main – Project has been awarded to St. Laurent and Son. Staff attended a pre construction meeting – start date in a couple weeks.

  • Park Ave Reconstruction – The entire roadway has been base paved.  The contractor is currently installing granite curb and sidewalks.  Surface pavement will be placed week of 8/21.  The project is on schedule to be completed by September 1, 2017

  • Turner Street sidewalks – The project has been completed.

  • Lake Street Reconstruction Project – The contract has been awarded to Gendron & Gendron, to date one tree is down, new gas mainsand water mains are being installed, contractor has started test pits.

  • Sopers Mill Bridge Rehab – Project has been awarded to Knowles Industrial Services. A preconstruction meeting has been held and the project has begun.  A new footing has been constructed on the north abutment, crews are now working on the north wall.

  • Cook Street Reconstruction – Longchamps working on drainage on Cook Street.

  • Academy Street/High Street -  Intersection Project – In design

  • Main Street/Mill Street/Broad Street - Intersection Project - In design

 

Contact Us

Submit